Road Closure Notice

West Dimond Boulevard intersections with Westpark Drive and Sand Lake Road will close to through traffic starting at 8:00 AM on July 5th for completion of the roundabout construction work.  See the flyer for more information:
Notice_1 Road Closure_Final_6-27-16

Pre-Construction Open House

Reference Documents

  1. Municipality of Anchorage – Context Sensitive Solutions (CSS)  MOA CSS Policy Adopted

Phase I Pre-Final DSR: West Dimond Blvd Phase I PRE-FINAL DSR – Report

Phase I APPENDICES

Phase I Pre-Final DSR Summary

This DSR addresses Phase I (Westpark Drive to Sand Lake Road) only. Final design and construction for Phase II (Jodhpur Street to Westpark Drive) will not advance until full construction funding becomes available. West Dimond Boulevard, Phase I, is a two-lane east-west collector without curbs or pedestrian facilities.

Phase I Objectives:

  1. Provide pedestrian and bicycle facilities within the project corridor;
  2. Improve safety by: improving horizontal and vertical geometry; separating vehicles from pedestrians and bicyclists; and calming traffic;
  3. Upgrade the roadway and intersections to current municipal road standards;
  4. Upgrade a public facility for adequate capacity for the future growth and development of the area for the next 20-30 years;
  5. Provide major intersections that will operate at adequate service levels in the future; and
  6. Reduce long-term road maintenance by providing greater durability to the road surface.

Phase I Recommended Alternatives (click on image to enlarge):

West Dimond Blvd - Westpark Drive to Sand Lake Road

West Dimond Blvd – Westpark Drive to Sand Lake Road

Single-Lane Roundabout at Westpark Drive Intersection with West Dimond Blvd.

Single-Lane Roundabout at Westpark Drive Intersection with West Dimond Blvd.

Single-Lane Roundabout at Sand Lake Road Intersection

Single-Lane Roundabout at Sand Lake Road Intersection